Sparkman Intermediate School

  • MCBOE voted on a name of the intermediate school on October 10, 2024

Grade Level

  • Intermediate: Grades 4 -6

Cost

  • Site Preparation Contract
    • $1,929,414.00
    • (Wiregrass Construction Company)
  • School Construction Contract
    • $43,766,524.00
    • (Bailey-Harris Construction)

Space

  • Square Footage: 113,000

Design Elements

  • 44 classrooms
  • four designated special needs classrooms
  • one art lab
  • one band room
  • two extended learning areas

Projected Capacity

  • The campus will open with an estimated 800 students, and the school will be built with a maximum capacity of 1200 students.

Grand Opening

  • Expected Opening Date: 2026-2027 school year

MCSS